Area: Annacarty
Started: January 1953
Finished: September 1953
Poles used: 1575
Line used (km): 130
Premises connected: 222
The figures above were sourced from our REO News magazine, to learn more about what these figures mean, visit our interactive map. The map above shows the area boundary and is from a digitised version of the original map used during the scheme.
Unfortunately no further information is available for this area in the REO magazine. As we work through the process of digitising our collections, if we find any other content for this area then we will publish it here. If you have any information or photos relating to the electrification of the area, please contact us. We would love to hear from you.