Area: Ballyconneely
Started: April 1958
Finished: June 1958
Poles used: 108
Line used (km): 8
Premises connected: 44
The figures above were sourced from our REO News magazine, to learn more about what these figures mean, visit our interactive map. The map above shows the area boundary and is from a digitised version of the original map used during the scheme.
As we work through the process of digitising our collections, if we find any other content for this area then we will publish it here.