A scanned, worn historical map from the 1940s of the  rural electrification area around Ballydooly. A hand‑drawn boundary outlines the region, including Ballymoe, Glinsk, Cartron, Tully, Mount Dillon  and Fuerty.

Area: Ballydooly
Started: April 1959
Finished: October 1959
Poles used: 1250
Line used (km): 105
Premises connected: 110
The figures above were sourced from our REO News magazine, to learn more about what these figures mean, visit our interactive map. The map above shows the area boundary and is from a digitised version of the original map used during the scheme.