“A scanned, worn historical map from the 1940s of the rural electrification area around Burncourt. A hand‑drawn boundary outlines the region, including Ballygoreen.Area: Buncourt
Started: November 1957
Finished: March 1958
Poles used: 715
Line used (km): 67
Premises connected: 125

The figures above were sourced from our REO News magazine, to learn more about what these figures mean, visit our  interactive map. The map above shows the area boundary and is from a digitised version of the original map used during the scheme.