Area: Galmoy
Started: December 1957
Finished: October 1958
Poles used: 1513
Line used (km): 137
Premises connected: 240
The figures above were sourced from our REO News magazine, to learn more about what these figures mean, visit our interactive map. The map above shows the area boundary and is from a digitised version of the original map used during the scheme.