Skip to Content
A scanned, worn historical map from the 1940s of the  	rural electrification area around Glynn. A hand‑drawn boundary outlines the region, including The power..

Area: Glynn
Started: November 1956
Finished: March 1957
Poles used: 743
Line used (km): 64
Premises connected: 130

The figures above were sourced from our REO News magazine, to learn more about what these figures mean, visit our  interactive map. The map above shows the area boundary and is from a digitised version of the original map used during the scheme.