Area: Kilfenora
Started: May 1959
Finished: December 1959
Poles used: 1295
Line used (km): 114
Premises connected: 223
The figures above were sourced from our REO News magazine, to learn more about what these figures mean, visit our interactive map. The map above shows the area boundary and is from a digitised version of the original map used during the scheme.