Skip to Content

A scanned, worn historical map from the 1940s of the  rural electrification area around Strandhill. A  hand‑drawn boundary outlines the region.Area: Strandhill
Started: August 1948
Finished: June 1949
Poles used: 1059
Line used (km): 83
Premises connected: 204

The figures above were sourced from our REO News magazine, to learn more about what these figures mean, visit our  interactive map. The map above shows the area boundary and is from a digitised version of the original map used during the scheme.