Area: Toor
Started: December 1960
Finished: April 1961
Poles used: 748
Line used (km): 65
Premises connected: 121
The figures above were sourced from our REO News magazine, to learn more about what these figures mean, visit our interactive map. The map above shows the area boundary and is from a digitised version of the original map used during the scheme.