A scanned, worn historical map from the 1940s of the  rural electrification area around Tully. A  hand‑drawn boundary outlines the region.Area: Tully
Started: October 1959
Finished: April 1960
Poles used: 1104
Line used (km): 95
Premises connected: 200

The figures above were sourced from our REO News magazine, to learn more about what these figures mean, visit our  interactive map. The map above shows the area boundary and is from a digitised version of the original map used during the scheme.